The construction of the operation and maintenance base for the Bałtyk II and Bałtyk III offshore wind farms will begin in Łeba later this year, employing around 100 specialists. Employment prospects and work on the construction of the base and offshore wind farms were discussed by representatives of investors at a meeting with the residents of Łeba and the surrounding area on March 19th.
- notifying the commencement of construction to the Chief Labor Inspectorate,
- notifying the commencement of construction to the County and Voivodship Construction Supervision Inspectorate,
- regular communication with townships (for example at the stage of issuing building permits),
- regular communication with suppliers and subcontractors in order to coordinate construction work,
- communication with energy distributors to inform them about the commencement of construction works and to arrange meetings,
- communication with lenders (including EBRD) and other financial institutions operating under the Equator Principles in compliance with the obligations imposed by the financial advisor,
- regular communication with local communities and residents (residents of neighboring areas, owners of properties leased for wind power plants, etc.).