Dębsk Wind Farm

The Dębsk Wind Farm project is executed by a special purpose vehicle Polenergia Farma Wiatrowa 3 Sp. z o.o. The Dębsk Wind Farm is located in the Żuromin township and in the Kuczbork Osada township in the Żuromin county in the Mazowieckie Voivodeship.

Decision on environmental conditions issued by the head of the Kuczbork Osada township for the project involving construction of the “Żuromin FW2” wind farm with a total maximum capacity up to 87 MW, which will consist of up to 29 wind turbines with capacity up to 3 MW each, underground connections to GPZ substations, internal access roads. Decision on environmental conditions issued by the Mayor of the Żuromin Township and City for the construction project of the “Żuromin FW3” wind farm with a total maximum capacity up to 99 MW, which will consist of up to 33 wind turbines with maximum sound power level of no more than 106.5 dB each and capacity up to 3 MW each.

121 MW

total capacity of the Dębsk Wind Farm

55

wind turbines

A permit for the construction of wind turbines with accompanying infrastructure has also been obtained in the project. Ultimately, the company has decided to build 55 wind turbines. The capacity of individual Vestas V110–2.2MW wind turbines will be 2.2 MW. The total installed capacity of the wind farm is planned at 44 MW.

The total installed capacity of the wind farm will be 121 MW. The scope of the project also includes the main power supply point (GPZ), underground infrastructure of power and control cables as well as access roads to individual wind turbines and service and assembly yards. The energy generated by the wind turbines at the Dębsk Wind Farm will be transmitted through underground cable lines to the GPZ substation. After being converted to high voltage, electricity will be transmitted via a 110 kV underground cable that is approx. 63 km long, to the GPZ Kruszczewo substation owned by the Energa group. Construction work commenced in Q2 2020 and is slated for completion in Q2 2022, and the occupancy permit and license should be received in Q3 2022.

Download:

Contact form

Kostomłoty Wind Farm

The Kostomłoty Wind Farm project is executed by a special-purpose vehicle Polenergia Farma Wiatrowa Dębice/Kostomłoty Sp. z o.o. and it will be located in the Kostomłoty township, Środa county in the Dolnośląskie Voivodeship.

In 2016, the Kostomłoty Wind Farm obtained permits for the construction of nine turbines, the main substation (GPZ), underground infrastructure of power and control cables, access roads to individual turbines, and assembly and maintenance yards. The building permits were amended in 2016, 2017 and 2018 to reflect the wind turbines that were ultimately selected and other minor changes.

27 MW

total wind farm capacity

3 MW

capacity of individual Vestas V136 wind turbines

According to the building permit (amended in 2018), the capacity of individual Vestas V136 wind turbines will be 3 MW. The total installed capacity of the wind farm will be 27 MW. Electricity will be transmitted from the GPZ Kostomłoty substation via a 110 kV cable line that is approx. 14 km long, to the GPZ Kąty Wrocławskie substation, which is owned by the Tauron group.

Construction work commenced in Q1 2021 and according to the plan, it should be completed Q2 2022, and the occupancy permit and license should be received in Q3 2022.

Download:

Contact form

Piekło Wind Farm

13.2 MW

the capacity of the wind farm will be

2.2 MW

the capacity of individual Vestas V110 wind turbines

The project is executed by two special-purpose vehicles, Polenergia Farma Wiatrowa 16 sp. z o.o. and Polenergia Farma Wiatrowa Piekło sp. z o.o. The Piekło Wind Farm is located in the Międzychód county. The environmental impact assessment procedure for the project has been completed and a decision on environmental conditions has been issued approving the construction of up to 14 wind turbines and the necessary infrastructure. The company ultimately decided to build six wind turbines. The capacity of individual Vestas V110 wind turbines will be 2.2 MW. The total installed capacity of the wind farm will be 13.2 MW.

On 26 November 2020, based on the announcement of 1 October 2020, an auction identified as “AZ/7/2020” for the sale of electricity from renewable sources was held. The 13.2 MW Piekło Wind Farm project won the auction “AZ/7/2020” and received support for 15 years. The works related to the Piekło Wind Farm project are currently at the construction preparation stage, which entails an update of existing approvals, selection of contractors, organization of financing. In December 2021, the Company’s corporate bodies gave the approval to launch the Piekło Wind Farm project. On 30 December 2021, the agreements for the supply and assembly of turbines for the Piekło Wind Farm came into effect upon payment of the relevant advances by companies executing the Piekło Wind Farm project under contracts signed with Vestas Polska sp. z o.o.

Construction is scheduled to begin in Q2 2022 and the construction and assembly works should be completed in Q2 2023.

Download:

Contact form

Grabowo Wind Farm

44 MW

planned total wind farm capacity

2.2 MW

the capacity of individual Vestas V110 wind turbines

The Grabowo Wind Farm is located in the Kolno county. The environmental impact assessment procedure for the project has been completed and a decision on environmental conditions has been issued approving the construction of up to 20 wind turbines and the necessary infrastructure. The capacity of individual Vestas V110 wind turbines will be 2.2 MW. The total installed capacity of the wind farm is planned at 44 MW.

The works related to the Grabowo Wind Farm project are currently at the construction preparation stage, which entails an update of existing approvals, selection of contractors, organization of financing. In December 2021, the Company’s corporate bodies gave the approval to launch the Grabowo Wind Farm project.

Construction is scheduled to begin in Q2 2022 and the construction and assembly works should be completed in Q3 2023.