Previous topic
Onshore wind farms
On 26 November 2020, based on the auction announcement of 1 October 2020, "AZ/7/2020" auction for the sale of electricity from renewable energy sources was held. All projects submitted by Polenergia S.A. won this year's RES auctions for new photovoltaic power plants. A portfolio of PV projects: Sulechów II, Sulechów III and Buk I with a total capacity of 28 MW will receive 15-year support.
Buk I photovoltaic farm project is being implemented by the special purpose vehicle Polenergia Farma Wiatrowa Rudniki Sp. z o.o. Buk I will be located on plots No. 409/1, 411/2, 729, 732, 733/1, 733/2, 734/1 within the village of Wielka Wieś, Buk Gmina, Poznań Poviat, Wielkopolskie Voivodeship.
Buk I project will consist of seven photovoltaic farms with a capacity of up to 1 MW each, with the necessary technical infrastructure. Total capacity of the farms will be 6.44 MWp.
The administrative procedure for issuing the decision on environmental conditions for Buk I was conducted by the competent authorities, i.e. the Mayor of Buk Gmina and Town. In the course of the administrative procedure, the State Sanitary Inspector, the National Water Management Holding Polish Waters and the Regional Directorate for Environmental Protection (RDOŚ) in Poznań were consulted. It was determined that there was no need to carry out environmental impact assessment for the planned project.
The procedure ended with the issuance of a decision on environmental conditions (document ref. No. IP.6220.24.2018 issued on 28 November 2018) permitting the construction and installation of nine photovoltaic farms with a capacity of up to 1 MW each, including the necessary technical infrastructure and staging. The project also received building permits. Construction works are scheduled to start in August 2021.
Sulechów II photovoltaic farm project is implemented by the special purpose vehicle Polenergia Farma Wiatrowa 17 Sp. z o.o. Sulechów II will be located on plots No. 124/4, 124/3, 142, 141, 8/28, 8/15 and part of plots No. 120/8, 120/5, 121/3, 122/3, 123/3 in Kruszyna section, Sulechów Gmina, Zielona Góra Poviat, Lubuskie Voivodeship.
Sulechów II project will consist of twelve photovoltaic farms with a capacity of up to 1 MW each, with the necessary technical infrastructure. Total capacity of the farms will be 11.714 MWp.
The administrative procedure for issuing the decision on environmental conditions for Sulechów II was conducted by the competent authorities, i.e. the Mayor of Sulechów. In the course of the administrative procedure, the State Sanitary Inspector, the National Water Management Holding Polish Waters and the Regional Directorate for Environmental Protection (RDOŚ) in Gorzów Wielkopolski were consulted. It was determined that there was no need to carry out environmental impact assessment for the planned project.
The procedure ended with the issuance of a decision on environmental conditions (document ref. No. GKR.6220.17.2018.MG issued on 18 October 2018) permitting the construction and installation of thirteen photovoltaic farms with a capacity of up to 1 MW each, including the necessary technical infrastructure and staging. The company will construct twelve photovoltaic farms, in accordance with the received building permits. Construction works are scheduled to start in June 2021.
Sulechów III photovoltaic farm project is implemented by the special purpose vehicle Polenergia Farma Wiatrowa Rudniki Sp. z o.o. Sulechów III will be located on plots No. 7/30, 7/40, 7/12, 7/83, 7/84 in Kruszyna section, Sulechów Gmina, Zielona Góra Poviat, Lubuskie Voivodeship.
Sulechów III project will consist of nine photovoltaic farms with a capacity of up to 1 MW each, with the necessary technical infrastructure. Total capacity of the farms will be 9.835 MWp.
The administrative procedure for issuing the decision on environmental conditions for Sulechów III was conducted by the competent authorities, i.e. the Mayor of Sulechów. In the course of the administrative procedure, the State Sanitary Inspector, the National Water Management Holding Polish Waters and the Regional Directorate for Environmental Protection (RDOŚ) in Gorzów Wielkopolski were consulted.
It was determined that there was no need to carry out environmental impact assessment for the planned project.
The procedure ended with the issuance of a decision on environmental conditions (document ref. No. GKR.6220.9.2019.MG issued on 28 November 2018) permitting the construction and installation of ten photovoltaic farms with a capacity of up to 1 MW each, including the necessary technical infrastructure and staging.
The company will construct nine photovoltaic farms, in accordance with the received building permits. Construction works are scheduled to start in July/August 2021.