Transportation of towers to the Szymankowo Wind Farm

Transportation of towers to the Szymankowo Wind Farm

The works in the Szymankowo wind farm site are under way.

The construction started in March this year and is scheduled to be completed in February 2021. So far all foundations have been completed – each with the diameter of 20 meters, built using 70 tons of reinforcement and 530 m3 of concrete. Two sections of the first Baltic Operator tower have been delivered. The next ones will be transported soon. The turbines are supplied by Siemens Gamesa. The Szymankowo Wind Farm will be composed of 11 wind turbines with the total capacity of 38 MW.

The project is executed with PBDI, Siemens Gamesa and Bilfinger.

Search results

Szanowny użytkowniku, w zgodzie z założeniami RODO potrzebujemy Twojej zgody na przetwarzanie danych osobowych w tym zawartych w plikach cookies. Dowiedz się więcej.

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close