The year 2025 marks the next chapter in the implementation of the Bałtyk 2 and 3 and Bałtyk 1 projects, which look to be very intense. There are many challenges ahead of the Companies, as the final investment decision for the Bałtyk 2 and 3 projects is scheduled to be made in Q1, and construction work is set to begin. The farms, with a total capacity of 1440 MW, will be located in the Polish economic zone of the Baltic Sea, between 22 and 37 km from the coastline.
In addition to the connection infrastructure, substation, landfall drilling, the construction of a service base in Łeba will also begin, which will serve as a logistics and operations center for the Bałtyk 2 and 3 offshore wind farms.
On the other hand, the Bałtyk 1 project, which will be 81 km from the shore, obtained in 2024, among other things, a decision on environmental conditions for the offshore wind farm and a decision approving a geological works project to detail information on ground conditions for the future foundation of wind turbines, substations and internal cables. CPT soundings were conducted on this basis. The results of the surveys will form the basis for determining the bearing parameters that guarantee the safety of the foundation of the structures. A milestone for Project Bałtyk 1 will be participation in an auction, the successful outcome of which will allow the project to be implemented.